Amaravati Outer Ring Road listed on NHAI portal; project cost estimated at ₹31,277 crore
The proposed Amaravati Outer Ring Road (ORR) has been listed on the National Highways Authority of India (NHAI) portal, marking a step forward for the major road infrastructure project in Andhra Pradesh.

The 195.13-km expressway has an estimated cost of ₹31,276.73 crore and is proposed to be executed under the Hybrid Annuity Model (HAM). Multiple clearance proposals for the project are reportedly under process.
The proposed six-lane, access-controlled corridor is intended to improve connectivity around Amaravati and strengthen road links between key locations in the capital region.
Earlier project details indicated that NHAI had invited bids for construction across four packages, covering more than 190 km of the main corridor and a spur road.
* Package 1: Kanchikacherla–Nandigama, 27.93 km, estimated at ₹2,975.47 crore.
* Package 2: Nandigama–Davuluru, 56 km, estimated at ₹2,864.69 crore.
* Package 3: Kolavennu–Kornepadu and Narakoduru spur, 55.8 km, estimated at ₹2,827.95 crore.
* Package 4: Kornepadu–Kanchikacherla, 55.5 km, estimated at ₹2,869.59 crore.
The package-wise estimates provided total approximately ₹11,537.70 crore, substantially below the overall project estimate of ₹31,276.73 crore. The difference may reflect different project scopes or stages of estimation and requires clarification from official documents.
The listing and ongoing clearance process are important developments for the Amaravati road network. However, the listing alone does not establish that all clearances have been secured or that construction has begun.