Chennai Metro phase-II achieves three TBM breakthroughs in just three days
Chennai Metro Rail Limited (CMRL) has achieved a notable tunnelling milestone under Phase-II, recording three Tunnel Boring Machine (TBM) breakthroughs on three consecutive days.

The latest breakthrough was achieved on Wednesday with the downline TBM ‘Adyar’ completing its drive at RK Salai Station on Corridor 3.
The three breakthroughs took place in quick succession. On September 29, Corridor 3 downline TBM ‘Kaveri’ broke through at KMC Station, followed by Corridor 5 downline TBM ‘Maruthan’ at Villivakkam Station on September 30. The latest breakthrough by ‘Adyar’ at RK Salai Station was completed on October 1.
The tunnelling works for the 12-km underground section of Corridor 3 between Kellys and Taramani are being executed by Larsen & Toubro, with eight TBMs deployed for the works.
The ‘Adyar’ TBM completed a 915-metre downline tunnel between Royapettah and RK Salai. The drive began on December 29, 2025, and was completed in 277 days.
During the tunnelling operation, the machine negotiated several critical structures along Royapettah High Road, including Peters Bridge, the EPFO building, Andhra School and several commercial establishments. The tunnel was constructed through silty sand at an overburden depth of around nine to 13 metres.
CMRL said 11 cutterhead interventions were carried out during the drive. Despite the challenging urban environment and existing structures along the alignment, the work was completed without major ground settlement or adverse impact on infrastructure.
The breakthrough marks the 10th TBM breakthrough under the TU02 contract, adding another milestone to the ongoing Chennai Metro Phase-II tunnelling works.