CMRL clears flyover construction above Teynampet, Nandanam Metro Stations
Chennai Metro Rail Limited (CMRL) has granted permission to the Tamil Nadu Highways Department to resume construction of the 3.2-km, four-lane elevated corridor between Teynampet and Saidapet along Anna Salai, including the challenging section directly above the operational underground Metro infrastructure.

Around 2.4 km of the 3.2-km corridor runs directly above the Metro tunnel, including a 460-metre stretch over the Teynampet and Nandanam Metro stations. Construction over these two stations had remained stalled for several months pending clearance from CMRL.
The clearance followed technical assessments aimed at ensuring that the flyover's foundations do not interfere with the underground Metro structures. The Metro tunnel beneath this section lies approximately 14–15 metres below Anna Salai, while the flyover foundations have been designed to extend only about seven metres from the road surface, according to officials cited in the report.
The project is being built using prefabricated steel components and has been described as the country's first elevated corridor constructed directly above an operational Metro tunnel. The estimated project cost is around ₹621 crore.
About 2.3 km of the flyover has already been completed, with 50 of the planned 69 piers erected. Permission has now been granted for the remaining work, including portal-frame construction over the Metro stations.
The Highways Department expects the corridor to be completed by March 2027, subject to construction and traffic-management requirements.