K-RIDE MD reviews progress of Bengaluru Suburban Rail and 48-km Baiyappanahalli–Hosur doubling projects
K-RIDE Managing Director Lakshman Singh inspected the progress of the Bengaluru Suburban Rail Project’s Corridor 4A, known as the Kanaka Line, and the 48-km Baiyappanahalli–Hosur railway doubling project on October 10, reviewing construction progress and key issues requiring resolution.

During the inspection of the Bengaluru Suburban Transport Project (BSTP) Corridor 4A, Singh reviewed works being executed by RVNL and Rithvik JV at Heelalige, Huskur and Kaggadasapura stations. Discussions focused on areas requiring improvement and the proposed elimination of Level Crossing No. 136.
The inspection also covered the Baiyappanahalli–Hosur railway doubling project, where officials examined issues at Chandapura and Benninganahalli.
At Chandapura, discussions centred on resolving the long-pending issue concerning the extension of National Highway 44. At Benninganahalli, the team reviewed the railway alignment and progress in removing existing obstacles to facilitate construction.
Senior officials from K-RIDE, the General Consultant, RVNL–Rithvik JV and the engineering team participated in the inspection.
The review is aimed at addressing project-level bottlenecks and improving execution across the suburban rail and railway doubling works.